State Route 9 Saratoga Creek Bridge
Caltrans began construction on the Saratoga Creek Bridge Rehabilitation on State Route 9 (SR-9), Saratoga, CA, in the spring of 2023. This project maintained safe and stable connectivity along State Route 9 between the City of Saratoga in Santa Clara County and the community of Felton in Santa Cruz County. Caltrans recommended replacing the bridge, due to seismic and structural concerns. The rehabilitation project allowed the newly replaced bridge to meet seismic safety regulations.
Major work on Saratoga Creek bridge was completed in December 2023. Additional work including erosion control and landscaping is ongoing. All work is scheduled to be completed by the end of September 2024.
Project History
Project Description
This project was to maintain safe and stable connectivity along State Route 9 between the City of Saratoga in Santa Clara County and the community of Felton in Santa Cruz County. Caltrans’ Office of Structure Maintenance and Investigations recommended replacing or retrofitting the Saratoga Creek Bridge (No. 37-0074), at post mile 4.9 due to seismic and structural concerns.
Work Description
Near Saratoga, at Saratoga Creek Bridge No. 37-0074. Replaced bridge while maintaining existing bridge outside façade.
Project At A Glance
KEY DATES
Start Construction....................... March 2023
End Construction........................ December 2023