Guadalupe Active Partnership for Signalization and CAPM to Santa Maria (GAPS-CAPM)
Project Description
ADA Curb Ramp and Sidewalk Improvements
The project will upgrade or replace 98 curb ramps to conform to American Disability Act standards. Approximately 5,550 linear feet of sidewalk will be added to the north and south side of Highway 166 starting at the intersection of Highway 166 and Highway 1. On the south side of Highway 166, the project will add approximately 630 feet of sidewalk past Flower Ave; on the north side of Highway 166, the sidewalk will end at Flower Ave.
Sign Panel and Guardrail Upgrades
The project will include 9 large sign replacements. Also, the project will upgrade approximately 1,637 linear feet of guardrail to meet the Manual for Assessing Safety Hardware standards.
Drainage
The project will include approximately 2,000 linear feet of drainage ditch improvements on the south side of Highway 166 from the Highway 1 intersection to 0.1 miles past Flower Ave. Sediment control features will be integrated into the ditch to help alleviate sediment build up during peak flows and farm runoff.
On the north side of Highway 166 from Highway 1 to Flower Avenue, a portion of the open drainage ditch running next to the highway will be culverted. The project will convert approximately 1,280 feet of the ditch into a closed culvert, including small sections of the ditch that run under roads intersecting Highway 166.
East of Flower Avenue, no roadside ditches will be impacted by the project.
Intersection Improvements
Highway 166 and Highway 1 Intersection
The project will replace the stop sign-controlled intersection at Highway 166 and Highway 1 with signalization. The roadway will be widened along Highway 1 and Highway 166 to accommodate additional turning lanes. The North, East, and South legs of the intersection will have left turn lanes added. The signals will incorporate Transportation Management Systems, which are electronic detection systems that help collect data on traffic patterns at the intersection.
Highway 166 and Obispo Street Intersection
The project will add signalization at the Highway 166 and Obispo Street intersection and will incorporate Transportation Management Systems.
Highway 166 and Flower Ave Intersection
The project will add a two-way stop sign for traffic control at the Highway 166 and Flower Ave intersection and add left turn lanes to the North, East, and South legs of the intersection.
Union Pacific Railroad
Improvements will be made on the Union Pacific Railroad at-grade crossing with the inclusion of a pre-signal. The pre-signal will be a traffic light that stretches across the road before the railroad crossing. A raised median will be added where the railroad crosses Highway 166 and signal arms will be placed on either side of the median. Roadway pavement marking and striping will be incorporated to align with these changes at and near the railroad crossing
Bike Lanes
Approximately 1.04 miles of Class 2 bike lanes will be added on the east and westbound lanes of Highway 166 from the intersection of Highway 1 to approximately 0.1 miles past Flower Ave.
Información sobre el proyecto en español
Project Benefits
Purpose
The purpose of the project is to:
- Preserve and extend the life of the existing pavement.
- Improve the collection of traffic data.
- Update guardrail to Manual for Assessing Safety Hardware standards.
- Replace signs and update curb ramps to meet American Disability Act compliance.
- Increase utility of intersections for drivers, pedestrians, and cyclists.
- Improve multimodal access.
Need
- The Caltrans Pavement Management System Report indicated State Route 166 is exhibiting minor surface distress and unacceptable ride quality, which if left uncorrected, will deteriorate to a major roadway rehabilitation need.
- Existing traffic census stations have reached the end of their service life or will be damaged during construction related activities.
- Sections of guardrails within the project limits do not meet the Manual for Assessing Safety Hardware standards and spot locations of curb ramps do not meet current Americans with Disabilities Act standards.
- According to the Guadalupe Mobility & Revitalization Plan, bike lanes and sidewalks on State Route 166 near the City of Guadalupe are insufficient for future development.
- The flow of traffic is projected to deteriorate over time and, if left uncorrected, will reach unsatisfactory levels.
Partnerships
- California Transportation Commission
- City of Guadalupe
- Santa Barbara County Association of Governments
- California Department of Fish and Wildlife
- Central Coast Regional Water Quality Control Board
- U.S. Army Corps of Engineers
Proposed Project Schedule
Process | Date |
---|---|
Virtual Public Meeting | May 2024 |
Final environmental document to be completed | August 2024 |
Right-of-way acquisition to be completed | December 2025 |
Design to be completed | April 2026 |
Advertise | July 2026 |
Construction to begin | November 2026 |
Construction to be completed | August 2027 |
Project Contact
Lucas Marsalek, Senior Environmental Scientist
Phone: 805-458-5408
Email: lucas.marsalek@dot.ca.gov
Laura Riccardelli, Environmental Scientist
Phone: 805-319-0163
Email: laura.riccardelli@dot.ca.gov
Meg Henry, Project Manager
Phone: 805-441-3792
Email: meg.henry@dot.ca.gov
Public Information Office, Caltrans District 5
Phone: 805-549-3318
Email: info-d5@dot.ca.gov
Documents
Accessibility Assistance: Caltrans makes every attempt to ensure our documents are accessible. Due to variances between assistive technologies, there may be portions of this document which are not accessible. Where documents cannot be made accessible, we are committed to providing alternative access to the content. Should you need additional assistance, please contact us at (916) 654-2852 or visit https://dot.ca.gov/request-ada-compliant-documents.
- Initial Study with Mitigated Negative Declaration (PDF)
- Physical copies will be available at the Caltrans District Office in San Luis Obispo, the Guadalupe Public Library, and the Santa Maria Public Library.
- Preliminary Project Plans
- Notice of Determination - August 19, 2024
- NEPA Categorical Exemption to be released - August 2024
Virtual Public Meeting Information
A virtual public meeting was held on May 16, 2024. A recap of that meeting can be found here: https://youtu.be/NhsEoOhN8So
Title VI Information
The California Department of Transportation (Caltrans) assures that no person shall, on the basis of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity receiving Federal financial assistance, as required by Title VI of the Civil Rights Act of 1964, as amended, the Civil Rights Restoration Act of 1987, and Federal Executive Order 12898 (Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations).
Caltrans will make every effort to ensure nondiscrimination in all of its programs and activities, whether they are federally funded or not, and that services and benefits are fairly distributed to all people, regardless of race, color, or national origin. In addition, Caltrans will facilitate meaningful participation in the transportation planning process in a nondiscriminatory manner.
Title VI Brochures
Title VI brochures in various languages